TOPIC: Critical Path Questions on the PMP Exam?

Critical Path Questions on the PMP Exam? 4 months 3 weeks ago #33292

  • Brian White
  • Brian White's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 0
Hi everyone,

I’m a few days out from my PMP exam and trying to fine-tune my review. For those who’ve taken it recently—how common were critical path calculation questions? Did you see more than one?

I just finished a course where most of my time was used drilling critical path formulas, but from what I’ve been reading here, it doesn’t seem to come up as often on the actual exam.

At this point, I’m just trying to figure out how much focus it deserves in these final days. Appreciate any insights!

Critical Path Questions on the PMP Exam? 4 months 2 weeks ago #33305

  • Erik Smith
  • Erik Smith's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 42
  • Karma: 2
  • Thank you received: 5
Hey Brian,

I have not taken the exam super recent (1 year ago), but from my experience there was only 1 question related to critical path.

If you understand the high level concept of identifying the critical path and recognizing when something deviates from it, then you should be good to go. Not many calculations were on the test during my exam.
Moderators: Yolanda Mabutas, Markus Kopko, Mary Kathrine Padua, Professor Kevin Reilly, John Paul Bugarin, Anusha Jayaram, Harry Elston, Jean Kwanda, Neil Baghurst PMP, Elena Zelenevskaia, Erik Smith, Joseph Flanders, Pablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login