fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: PM study coach - TCPI demystified

PM study coach - TCPI demystified 14 years 1 month ago #1352

  • Gerald Derflinger
  • Gerald Derflinger's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Hi Cornelius,

I have a question on the TCPI demystified paper from the PMstudy coach cost mgmt. lesson. On page 3 there is a calculation of the required EAC to be able to calculate the TCPI (based on EAC). Here are the numbers from Frank's dog house:

status on day 3:

BAC=500 USD
EV=300 USD
AC=400 USD

To calculate TCPI, we first need to calculate EAC. Per definition the EAC=AC+ETC (one possibility). So, corresponding to this example we have to make a new forecast on ETC as we need to earn 2 USD value for every 1 USD we spend (as posted in the example). Therefore new ETC = 400 USD ( 200 USD / day).

Now, in the calculation of the EAC there is the EV used instead of AC - so, can you tell me please what is the reason for this? I thought we need AC to calculate the EAC?

I look forward to your reply.

thanks, Gerald

Re:PM study coach - TCPI demystified 14 years 1 month ago #1353

  • Nitin Shekhar
  • Nitin Shekhar's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
TCPI demontrated overall performance and is calculated by dividing the Total work remaining by Total fund remaining. In this case,
the total work remaining will be BAC-EV and
Total fund remaining will be BAC-AC
thus, the formula is TCPI = (BAC-EV)/(BAC-AC)

Re:PM study coach - TCPI demystified 14 years 1 month ago #1354

  • Gerald Derflinger
  • Gerald Derflinger's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
Thx for feedback first of all.

I agree to your formula in principle, but when you look at the example following to your posted formula, it is necessary also to calculate the TCPI based on EAC:

TCPI = (BAC-EV) / (EAC-AC)

To be able to calculate this formula now, it is necessary to calculate actual EAC first. Therefore 2 possible way would work:

1) EAC = AC + BAC - EV
= 400 + 500 - 300
= 600

2) EAC = AC + ETC
= 400 + 400
= 800

In this example you have 400 USD, 200 USD per day, 2 days left. So, described on the paper it is calculated as following:

EAC = 700 -> (EV + 400) , EV = 300 (3 days are already over, 100 USD per day)

As you can see here, in the example ones is using EAC = EV + ETC instead of EAC = AC + ETC

Do you know why this has been chosen?

thx, gerald

Re:PM study coach - TCPI demystified 13 years 11 months ago #1501

  • Gerald Derflinger
  • Gerald Derflinger's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 0
I almost forgot on my entry here :-) sorry for that - comming back to it, maybe does anyone know the answer on it? Or can anyone correct me? (if my thoughts are wrong)

would be really appreciated...

thx,gerald
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login