Reply: Control Charts - Rule of Seven

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Control Charts - Rule of Seven

Max. showing the last 6 posts - (Last post first)
14 years 1 month ago #1317

Orkun Toros

Orkun Toros's Avatar

I am confused about the "out of control" process indication on a control chart. According to my knowledge, a process is out of control if:

-A data point falls outside of the upper or lower control limits.
-7 data points in a row fall above or below the mean.
-7 data points in a row trending up or down (crossing the mean).

The PMBOK Guide (8.2.3 page 196) states that "a process is considered out of control when a data point exceeds a control limit or if seven consecutive points are above or below the mean". I listened PrepCast 08.04 and it also said that "Seven times fall onto the same side of the mean-->Investigate".

As I understood from the language in the PMBOK Guide and the PrepCast, if out of 7 consecutive data points, 4 fall under and 3 fall above the mean, the process should not be counted as out of control.

I surely will take whatever PMBOK Guide says but I wanted to verify first.

Thanks so much,

Orkun