I have a math question in regard of the Project network node. in the question the following information is given :
ES:21 LS: 37 LF:39
And the question is to calculate EF, Duration and Float.
I started the problem with calculating the Duration with the following formula LS-LF +1 (37-39 +1 ) and the answer is 3 days.
I got the answer wrong because I was following the Math rule and calculated -1 and I should have been doing 39-37 +1 = 3. But by switching the 37 and 39, I'm not following the math formula anymore... and this is what i don't grasp.

Is anyone able to provide some clarity and explain why we are aloud switch number .

Thank you,

Project Network Node (math question) 3 years 1 month ago #30425

  • Ehizogie Ero-Brown
  • Ehizogie Ero-Brown's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
What helps me is thinking of it practically, day 39, day 38 and day 37. So for duration it is 3 days.

Project Network Node (math question) 3 years 1 month ago #30438

  • alex
  • alex's Avatar
  • Visitor
  • Visitor
The float is 16 and the Duration is 3
LS-ES = Float
37-21 = 16
LF-EF=Float
LF-EF=16
39-EF=16
EF=23
EF=ES+D-1
23=21+D-1
D=3

Project Network Node (math question) 3 years 4 weeks ago #30472

  • LS
  • LS's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
LF - LS = EF - ES -> 39 - 37 = EF - 21 => EF = 23
Duration = LF - LS + 1 = EF - ES + 1 = 3 days
Float = LF - EF = LS - EF = 39 - 23 = 37 - 21 = 16 days
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMPElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login