fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Lag Question

Lag Question 3 years 3 months ago #30229

  • Walter Ramos
  • Walter Ramos's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
The answer to the following question es 17. I think I know why but I am not sure if my answer is logical. Can someone explain the reasons. The book does not explain it. Thanks!

Activity X is 14 days and there is a 13-day lag. The best-case time to complete Activity X and Activity Y is 30 days. What is the duration of Y if there is a finish-to-finish relationship?

Anybody?
Last edit: by Walter Ramos. Reason: Didn't pertain to the question
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMPElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login