fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Lag Question

Lag Question 1 year 8 months ago #30229

  • Walter Ramos
  • Walter Ramos's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
The answer to the following question es 17. I think I know why but I am not sure if my answer is logical. Can someone explain the reasons. The book does not explain it. Thanks!

Activity X is 14 days and there is a 13-day lag. The best-case time to complete Activity X and Activity Y is 30 days. What is the duration of Y if there is a finish-to-finish relationship?

Anybody?
Last edit: by Walter Ramos. Reason: Didn't pertain to the question
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaBrent Lee

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login