TOPIC: What the Difference Between (RTM) & The Requirements documentation?

What the Difference Between (RTM) & The Requirements documentation? 1 year 6 months ago #29817

  • Francois Sannan
  • Francois Sannan's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Anyone knows the difference between the requirements documentation and the Requirements Traceability Matrix (RTM) ?
Thanks

What the Difference Between (RTM) & The Requirements documentation? 1 year 6 months ago #29820

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1981
  • Karma: 118
  • Thank you received: 604
To put it into its simplest form:

The requirements documentation is one or more documents where you write down all the requirements for your project.

The requirements traceability matrix on the other hand is a table (or spreadsheet or some feature of your PM software) that takes all the requirements and maps them to the deliverables to ensure that each requirement that you have is actually satisfied.

See PMBOK Guide Glossary: 6th edition page 719 or 7th Edition page 247
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Last edit: by Cornelius Fichtner.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login