fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Question about Risks that do occur

Question about Risks that do occur 1 year 11 months ago #29330

  • Susan D
  • Susan D's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
I understand that a risk is something that hasn't happened but might, and that an issue is something that has happened. But in terms of test questions, what are we supposed to do "first/next" if a risk materializes? If a risk materializes, it becomes an issue. So do you update the risk register? Update the issue log?

Question about Risks that do occur 1 year 11 months ago #29332

  • Brian Nesbitt
  • Brian Nesbitt's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 8
  • Karma: 1
  • Thank you received: 2
If a known risk materializes (triggered) it has been realized. Review the risk register to identify the risk owner, risk response (if planned) is then implemented by the risk owner.
If a new risk is identified (during monitoring/controlling), risk register updated and subsequent risk processes conducted.
As you mentioned, an issue has already happened and is something that requires a resolution. The issue log is updated, not the risk register.

Question about Risks that do occur 1 year 11 months ago #29334

  • Smitha Anna Jacob
  • Smitha Anna Jacob's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Thanks Brian. Can you help to differentiate between a risk and an issue ?

Question about Risks that do occur 1 year 11 months ago #29335

  • Brian Nesbitt
  • Brian Nesbitt's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 8
  • Karma: 1
  • Thank you received: 2
Risks (threats and opportunities) may or may not occur.

Issues have already happened (are current), impact project performance, and need resolution.

Question about Risks that do occur 1 year 11 months ago #29347

  • Smitha Anna Jacob
  • Smitha Anna Jacob's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Thanks Brian
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login