14 years 2 months ago #1174

Cornelius Fichtner

Cornelius Fichtner's Avatar

John,

You are correct. We noticed this some time back and it's included in our Errata Sheet - see the PDF that you received with E00.03.
14 years 3 months ago #1168

John Chan

John Chan's Avatar

I just finished the Advanced Cost Theory PodCast (E07.05). The example for Present Value appears to be wrong. The PV of a $1M project with r=12% and n=3 should be $711780.

Is there a document which tracks all errata? I tried to search the forums but didn't find it.

Thanks.

-John