TOPIC: Error in PM Prepcast: Advanced Cost Theory

Error in PM Prepcast: Advanced Cost Theory 10 years 3 months ago #1168

  • John Chan
  • John Chan's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
I just finished the Advanced Cost Theory PodCast (E07.05). The example for Present Value appears to be wrong. The PV of a $1M project with r=12% and n=3 should be $711780.

Is there a document which tracks all errata? I tried to search the forums but didn't find it.

Thanks.

-John

Re:Error in PM Prepcast: Advanced Cost Theory 10 years 3 months ago #1174

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1637
  • Karma: 56
  • Thank you received: 308
John,

You are correct. We noticed this some time back and it's included in our Errata Sheet - see the PDF that you received with E00.03.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login