Hello everyone,
I had a quick question, when is the Stakeholder Engagement Matrix made? I feel I've read in previous prepcast questions that it was made as an output of the Stakeholder Engagement Plan.
I vaguely remember because of that, in one question the existence of the plan invalidated a question about the Plan because the existence of the Assessment Matrix meant that the engagement plan must have occurred already.
However, someone with free exam resources (I often find myself not agreeing with the answers based on what I've learned from the prepcast exam) had a similar question saying they identified stakeholders who were resistant to a project in the stakeholder assessment matrix. How can the PM align this stakeholder's expectation?
and the answer was "to create the stakeholder engagement plan", so which process occurs first?