fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: PMP Question

PMP Question 2 years 10 months ago #27324

  • Mobolaji Moshood
  • Mobolaji Moshood's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
What do you do when you want to change from predictive to agile but your stakeholder is resistant, because it is proven that in the past projects, a predictive life cycle is what your team has been using to succeed in the previous projects

Question 2: What do you do when your project has decided to change its life cycle, do you pause all project work ?
Last edit: by Mobolaji Moshood.

PMP Question 2 years 10 months ago #27333

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 820
  • Karma: 17
  • Thank you received: 114
I would ask, is it wise to change approach mid-way through a project, especially if a stakeholder is resistant to that and the other approach is already proven? It's normally better (in my experience) to decide on a method at the beginning. I'm sure you could switch, but it's just going to take a lot of communication, engagement, meetings, discussion and agreement.
---
Elizabeth Harrin
Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com

PMP Question 2 years 10 months ago #27364

  • Erzsébet Budai, PMP
  • Erzsébet Budai, PMP's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 4
  • Thank you received: 2
A change request is a must in this case. You are changing the lifecycle approach which is part of the project management plan (in the planning process you have agreed with your stakeholders to use waterfall and they all agreed to it, approved it but now it is changing...). Since the plan has already been approved and now you're in the execution stage, a CR is needed because you want to go back to the plan and change the component of the plan, the lifecycle approach.
Last edit: by Erzsébet Budai, PMP.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login