2 years 10 months ago #27363

Erzsébet Budai, PMP

Erzsébet Budai, PMP's Avatar

Hello

Workaround is applied when an unknown (a previously UNidentified) risk occurs and you need to come up with a solution like immediately. You didn't plan for it, but it occurred and now you have to manage it. Contingency is for already (previously) identified risks.
Active acceptance is a high-level definition.
2 years 11 months ago #27224

John Bickel

John Bickel's Avatar

www.pmlearningsolutions.com/blog/fallbac...ategy-pmp-concept-33

Here is a learning tool for you on CRS. Logically what is a work around? I feel a work around is the same or closely like a mitigation strategy that you put in place to remove the risk before it happens but after identified.
CRS I feel is the same as disaster recovery plan (DRP) in the event something happens this is my strategy to counter act it. Active acceptance? Well just as it says you know it is there, understand the consequences and "let it ride"
2 years 11 months ago #27208

Trying my best

Trying my best's Avatar

Hi all

With respect to Risk Management - What is the difference between Workaround, Contingent response strategy and Active acceptance.

I find all 3 very confusing and overlapping . TIA