fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: How do you when help a customer submit a C/R if he does not agree with CCB

How do you when help a customer submit a C/R if he does not agree with CCB 3 years 1 month ago #26745

  • Sharon S
  • Sharon S's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 176
  • Karma: 2
  • Thank you received: 15
How do you when help a customer submit a C/R if he does not agree with CCB or when to tell him all CCB decisions are final Both answers on two different questions were correct. How do I know when to do what?

How do you when help a customer submit a C/R if he does not agree with CCB 3 years 3 weeks ago #26876

  • Kyle Kilbride, PMP
  • Kyle Kilbride, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 121
  • Karma: 7
  • Thank you received: 49
This is a bit difficult to answer without more specific details. In general the customer would have agreed to the Change Management Procedures for the project (Change Management Plan). We always try to keep the customer happy, but also must keep in mind what was agreed to. We can always help submit a change request, but disposition would be subject to the Change Management Plan and CCB as appropriate.
Regards,
Kyle Kilbride, P.Eng, PMP
PMPrepCast Community Moderator

How do you when help a customer submit a C/R if he does not agree with CCB 3 years 3 weeks ago #26879

  • Sharon S
  • Sharon S's Avatar Topic Author
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 176
  • Karma: 2
  • Thank you received: 15
Concur, CCB is final but when would a PM assist a stakeholder to submit a C/R if the stakeholder does not agree with the CCB and when does the PM just tell the stakeholder, just accept it (CCB decision).
Last edit: by Sharon S.

How do you when help a customer submit a C/R if he does not agree with CCB 3 years 3 weeks ago #26889

  • Kyle Kilbride, PMP
  • Kyle Kilbride, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 121
  • Karma: 7
  • Thank you received: 49
It really depends on the context of the question, there's no rules you can use or memorize. I would say in general you can help facilitate the submission of a change request, but disposition of that change request is subject to your project's Change Management Plan. In my experience if a Customer has a scope change and the contract allows for additional compensation those changes are usually accepted.
Regards,
Kyle Kilbride, P.Eng, PMP
PMPrepCast Community Moderator
The following user(s) said Thank You: Sharon S
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login