TOPIC: Change request or no change request

Change request or no change request 5 years 10 months ago #25033

  • Zahi Ismail
  • Zahi Ismail's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 6
  • Thank you received: 0
Dears,
I came across a scenario where a change in the resources requirements is needed to continue the work. As far as I know, the resources requirements is not a controlled document. will this trigger a domino effect where a change in a controlled document will be needed and hence we need a change request?
same question if the change is needed in the requirements documentation.

Change request or no change request 5 years 10 months ago #25170

  • Elizabeth Harrin
  • Elizabeth Harrin's Avatar
  • Offline
  • Platinum Boarder
  • Platinum Boarder
  • Posts: 819
  • Karma: 16
  • Thank you received: 114
If a change in resources was required, I would not raise a change request. If a change in requirements was requested, I would.
---
Elizabeth Harrin
Moderator

Follow: twitter.com/corneliusficht
Like: www.facebook.com/PrepCast/
Subscribe: www.project-management-podcast.com
Moderators: Yolanda Mabutas, Markus Kopko, Mary Kathrine Padua, Professor Kevin Reilly, John Paul Bugarin, Anusha Jayaram, Harry Elston, Jean Kwanda, Neil Baghurst PMP, Elena Zelenevskaia, Erik Smith, Joseph Flanders, Pablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login