fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: A few assumptions. Need confirmation.

A few assumptions. Need confirmation. 3 years 5 months ago #24496

  • Rahul Vadakke Veetil PMP
  • Rahul Vadakke Veetil PMP's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Thank you received: 2
1. Who approves Project Management Plan, is mentioned in OPA.
2. To whom the final deliverable is transferred, is mentioned in the Project Management Plan.
3. WBS and Final Report are mandatory documents for a project. Communication Management Plan is not.
4. Seller Performance Report in a project will be included in Procurement Documentation and will eventually be part of OPA.
5. If a Physical Resource has to be reserved in advance so that it is available on time, it must be done by updating the OPA.
6. When an issue that is business-critical occurs, the first thing to do is to notify the Project Sponsor. If not business-critical, the first thing to do is to add it to the 'Issue log'.
Please confirm. Thank you.
Last edit: by Rahul Vadakke Veetil PMP.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login