fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Where is Acceptance criteria located?

Where is Acceptance criteria located? 3 years 5 months ago #24463

  • Kabilan Kangeyan
  • Kabilan Kangeyan's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
A question regrading Acceptance criteria:

Where is Acceptance criteria located?
Is it in 'Requirement documentation' or 'WBS' .. I see contrasting answers in different reading materials.

Where is Acceptance criteria located? 3 years 5 months ago #24473

  • Charlie
  • Charlie's Avatar
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 36
  • Thank you received: 3
I think that are in the scope statement which is output of the the define scope and this is because the acceptance criteria relate to the deliverables (which have to be accepted) and not to the requirements (which have to be fulfilled). Any other views out there?
Last edit: by Charlie.

Where is Acceptance criteria located? 3 years 5 months ago #24481

  • Lu Bai
  • Lu Bai's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 17
  • Karma: 1
  • Thank you received: 8
Acceptance Criteria is in
5.3.3.1 Project Scope Statement
5.4.3.1 WBS Dictionary, more detailed and focusing on each specific work package

I don't think it's in the Requirements Documents. I performed a search in my electronic PMBOK.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login