Reply: Sequence of tasks in Close project

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Sequence of tasks in Close project

Max. showing the last 6 posts - (Last post first)
3 years 5 months ago #24322

Kyle Kilbride, PMP

Kyle Kilbride, PMP's Avatar

I really don't think there's a prescribed order, but rather activities that need to be completed in a logical order. This would be ensuring administrative closure (e.g. reallocating resources and confirming acceptance of deliverables) of the project, completion of any contractual agreements (e.g. finalizing any remaining open claims),and other activities related to project closure (like you mentioned measuring stakeholder satisfaction, lessons learned, etc.).

Remember, the customer accepts the deliverables in Validate Scope, we confirm that acceptance in Close Project. But I would be less concerned with the order of these items and more concerned with understanding the required activities. Keep in mind that the Lessons Learned register would be updated throughout the phase and updating the OPAs would be one of the last logical steps.
3 years 5 months ago #24312

Rahul Vadakke Veetil PMP

Rahul Vadakke Veetil PMP's Avatar

I am listing what I understand as the correct order of steps in the Close project process group. Please confirm.

1. Confirm customer acceptance of deliverables.
2. Create the Final report.
3. Update lessons learned register and add the register to the lessons learned repository. Update OPA.
4. Transfer the deliverables to the customer.
5. Measure stakeholder satisfaction.