Hi there,
on the exam simulator I came accross one question ralated to what a Project Manager shouldn't do as part of 'close project or phase' process. Among the different possible answers 'closing procurements with vendors' was the correct answer. I obviously answered the question wrong. After reviewing the question, I understood that my decision of not selecting the correct answer was linked to what I had read on Rita's Process Chart. Under the Closing process group on Rita's Process Chart 'Complete final procurement closure' is one of the efforts of a PM. I totally understand that closing procurement with vendors is a task performed under the 'control procurements' process, though from Rita's book it seems that any outstanding procurement can still be closed during the 'Close project or phase' process.
Is there any concensus on this or did I misunderstand Rita's closing guidelines?