fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Acceptance criteria Vs Success criteria of the project

Acceptance criteria Vs Success criteria of the project 3 years 6 months ago #23906

  • Rahul Vadakke Veetil PMP
  • Rahul Vadakke Veetil PMP's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Thank you received: 2
I know that Project Charter will have the success criteria and approval requirements for the project. Project Scope Statement has the acceptance criteria for the project deliverables.

What is then the difference between acceptance criteria and success criteria? It is very confusing.

Acceptance criteria Vs Success criteria of the project 3 years 6 months ago #23914

  • Gabriella Dellino, PMP
  • Gabriella Dellino, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 266
  • Karma: 24
  • Thank you received: 93
Hi Rahul,

success criteria refer to what makes your project successful with respect to a given set of (measurable) project objectives. Did the project meet them?
Acceptance criteria, instead, refer to the conditions a project deliverable has to meet in order to gain acceptance from the customer.

Gabriella
Gabriella Dellino, PhD, PMP
PMPrepCast Community Moderator
The following user(s) said Thank You: Rahul Vadakke Veetil PMP

Acceptance criteria Vs Success criteria of the project 3 years 6 months ago #24029

  • Rahul Vadakke Veetil PMP
  • Rahul Vadakke Veetil PMP's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Thank you received: 2
Hi Gabriella,

I understand. But aren't they mostly overlapping?

Rahul

Acceptance criteria Vs Success criteria of the project 3 years 6 months ago #24038

  • Jack Lee
  • Jack Lee's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
I agree, Don't these two terms mean the same things.
Or can one of the explanation be, you need to have all the deliverables accepted, before you can call the project successful.
So Success criteria is a boarder phrase than acceptance criteria?
Last edit: by Jack Lee.

Acceptance criteria Vs Success criteria of the project 3 years 6 months ago #24053

  • Gabriella Dellino, PMP
  • Gabriella Dellino, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 266
  • Karma: 24
  • Thank you received: 93
Hi Rahul and Jack,

for sure acceptance criteria and success criteria are related to a certain extent. However, the way I see it, they operate at different levels; i.e., deliverable vs. project. So they focus on different aspects; we may say performance vs. requirements.
A project can be successful because it reached a target goal; e.g., improve a given metrics by 50%. This is not something to measure to decide whether the customer will accept a specific deliverable for that project. Instead, you (as the customer) may accept or reject a project deliverable based on the degree it meets the requirements. This is why the "Validate Scope" process derives "Accepted deliverables" as an output from the Requirements Mgmt plan, documentation, and traceability matrix (among other inputs).

Hope this clarifies a bit better the difference between the two.

Gabriella
Gabriella Dellino, PhD, PMP
PMPrepCast Community Moderator
The following user(s) said Thank You: Jack Lee

Acceptance criteria Vs Success criteria of the project 3 years 6 months ago #24066

  • Rahul Vadakke Veetil PMP
  • Rahul Vadakke Veetil PMP's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 72
  • Thank you received: 2
Thank you, Gabriella.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login