fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: risk prioritization query

risk prioritization query 3 years 6 months ago #23668

  • Deepti Bhattacharya
  • Deepti Bhattacharya's Avatar Topic Author
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 41
  • Thank you received: 7
Your sponsor is not happy with the process you have used to prioritize risks. She wants you to use more stringent ways to re-prioritize risks and come back to her.
which process are you currently in.

1) identify risks
2) perform quantitative risk analysis
3) perform qualitative risk analysis
4) monitor risks

The correct answer is 2. I chose 4. My logic was they are doing risk audit, and have discovered issue with the process of risk prioritization as a result of the same. I agree next process because of sponsors demand would be answer 2. But question asked which process are you currently in

question from eduhubspot

risk prioritization query 3 years 6 months ago #23700

  • Felix Kamanga, PMP
  • Felix Kamanga, PMP's Avatar
  • Offline
  • Senior Boarder
  • Senior Boarder
  • Posts: 67
  • Karma: 5
  • Thank you received: 14
Hi Deepti,

I think the correct answer is (3) because risks are prioritized during the qualitative risk analysis. Here, the probability of occurrence of risks is expressed in a scale (one to five for example).
If the sponsor asks for a more stringent analysis, then the quantitative risk analysis can be used. Here, the probability of occurrence of risks is expressed in percentages.
Felix Kamanga, PMP
Community Moderator
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login