TOPIC: Control limits definition

Control limits definition 3 years 7 months ago #23165

  • Savitri Biju
  • Savitri Biju's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
Rita Mulcahy says "Control charts are established in MQ" and then in the exercise it mentions "acceptable range of Control chart is determined in Plan Quality". What is the difference between both statements. My understanding is that all definitions for quality happen in Plan Quality process and hence control limots would be defined in Plan quality process. Please clarify and explain

Control limits definition 3 years 7 months ago #23168

  • Gabriella Dellino, PMP
  • Gabriella Dellino, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 266
  • Karma: 24
  • Thank you received: 93
Hi Savitri,

Plan Quality Management is the process where you identify quality standards and requirements, and this may include defining control and specification limits; e.g., whether the usual +/- 3 sigma can be acceptable, or a more restrictive measure should be adopted.
Control Charts - as the graphical representation of the variables you measured to describe a given process - are then used as one of the Control Quality Tools&Techniques to determine whether that process is under control.

Gabriella
Gabriella Dellino, PhD, PMP
PMPrepCast Community Moderator
The following user(s) said Thank You: Savitri Biju
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login