Referring to the question on Exam 4 (QID: 612353),
You are developing the project management plan for your project. You want to know if there is any relevant information from the past projects that can help you with your task.
What should you do?
A. Review the lessons learned register
B. Research the OPA
C. Meet with a project manager who managed similar past projects
D. Check with EEF for lessons learned from the past projects
Can I just confirm, is it that "B" should be the "default" answer?
Are there any specific scenarios that we can choose "C" as the answer, if yes, what are the scenarios?