fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Does any one have any idea how to approach this PERT question?

Does any one have any idea how to approach this PERT question? 5 years 11 months ago #22623

  • Ali MOMENZADEHPISHROO
  • Ali MOMENZADEHPISHROO's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 10
  • Thank you received: 0
Together with your team, you applied three-point estimation on a critical path
which consists of two activities.
The following duration uncertainties are all calculated assuming a ±3sigma
confidence interval.
The duration uncertainty—defined as pessimistic minus optimistic estimate—of
the first activity is 18 days; the second estimate has an uncertainty of 24 days.
Applying the PERT formula for paths (beta distribution), what is the duration
uncertainty of the entire path?

o 21 days
o 30 days
o 42 days
o No statement is possible from the information given
FROM OLIVER LEMANN FREE SAMPLES
Last edit: by Ali MOMENZADEHPISHROO.

Does any one have any idea how to approach this PERT question? 5 years 11 months ago #22632

  • Gabriella Dellino, PMP
  • Gabriella Dellino, PMP's Avatar
  • Offline
  • Gold Boarder
  • Gold Boarder
  • Posts: 266
  • Karma: 24
  • Thank you received: 93
Wow, Ali! That truly is a tough one!

Let me recap the assumptions here:
1. Two activities on the critical path
2. Activity duration following a Beta distribution
3. Duration uncertainty (i.e., standard deviation, sigma) known for each activity.
Please notice that the description here sounds a bit misleading to me. In fact, if you assume a beta distribution, the standard deviation is sigma = (P - O)/6, where P and O are the most pessimistic and most optimistic durations, respectively. Not that we will use this formula to solve this problem, but reading it as P - O confused me in the beginning.
4. Confidence interval as +/- 3sigma. This won't be needed to solve our problem ;)

Now, from some statistical theorems, we know that the variance of the project is equal to the sum of the variances of the activities on the critical path. In our case:
var_p = var_1 + var_2 = (sigma_1)^2 + (sigma_2)^2 = 18^2 + 24^2 = 900
So the standard deviation for the project (i.e., its duration uncertainty) is sigma_p = sqrt(var_p) = 30.

Therefore the correct answer should be option B.

That said, I've never seen anything like this in the actual exam, nor even in the exam simulations I practiced. Thanks for sharing it.

Gabriella
Gabriella Dellino, PhD, PMP
PMPrepCast Community Moderator

Does any one have any idea how to approach this PERT question? 5 years 11 months ago #22649

  • Ali MOMENZADEHPISHROO
  • Ali MOMENZADEHPISHROO's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 10
  • Thank you received: 0
Awesome !Good job
Thanks very much Gabriella
Moderators: Yolanda MabutasMarkus KopkoMary Kathrine PaduaProfessor Kevin ReillyJohn Paul BugarinAnusha JayaramHarry ElstonJean KwandaNeil Baghurst PMPElena ZelenevskaiaErik SmithJoseph FlandersPablo Andres Loayza

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login