6 months 3 weeks ago #16896

Rachel Madrid

Rachel Madrid's Avatar

Correct Answer: A

The creation of a user story to demonstrate the product increment developed in the iteration allows the team to allocate dedicated time to get prepared for the demonstration.

Reference: User Stories Applied: For Agile Software Development, Mike Cohn, 2004, User story

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Want more PMI-ACP exam sample questions? Just go to free.pm-exam-simulator.com and try the PM Exam Simulator free for 7 days.

OSP International LLC has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI)®. As a PMI® Registered Education Provider (R.E.P.), we have agreed to abide by PMI established quality assurance criteria.

“PMI” and “PMI-ACP” are registered marks of Project Management Institute, Inc.
6 months 3 weeks ago #16883

Harsh Anand

Harsh Anand's Avatar

It must be A.
6 months 4 weeks ago #16864

Axtel PMI-ACP

Axtel PMI-ACP's Avatar

I found a very similar question in the PMI ACP Prepcast simulator.

Here´s the explanation related to this question:

"The Team puts Stories in the Sprint Backlog in order to hold (or contain) a budget for the Story Points that the Team knows it´s going to need to spend on these things. We call these Stories PlaceHolder Stories, as they hold a place in our Sprint Backlog for Stories in a general category that the team doesn´t know the details about yet".
7 months 11 hours ago #16831

Axtel PMI-ACP

Axtel PMI-ACP's Avatar

It should be A!

But it seems so straightforward that I might be wrong.
7 months 1 day ago #16812

Rachel Madrid

Rachel Madrid's Avatar

Here is our free PMI-ACP Exam sample question of the week. This question is taken from The PM Exam Simulator at www.pm-exam-simulator.com/pmi-acp

An agile team needs to demonstrate a product increment at the end of every iteration. What should an agile practitioner recommend that the team do to make sure that they have adequate time to get prepared for the demonstration?

A. Create a user story for conducting the demonstration
B. Hire an external expert to handle the demonstration
C. Track the task with a project management plan
D. Delay the demonstration to the next iteration

Hint: What guides what the team works on?