Thanks for the response. I completely agree with your perspective. I am preparing for PMI ACP and came across the following question. Hence the doubt. What do you suggest could be the right answer?

During a sprint review, the product owner identifies a required improvement for a feature’s UI delivered during the sprint. What should the product owner do next?
Create a user story and put it in product backlog for prioritization and validation by the customer
Create a user story and prioritize it for the next sprint

Thanks,
Sadhana
4 years 2 weeks ago #20272

Yazmine Darcy

Yazmine Darcy's Avatar

Hello Sadhana,

Technically speaking, the product owner is the "voice of the customer". As such, the product owner is primarily responsible for product backlog refinement in terms of " building the right thing".

From your question, you imply that there is an "internal" product owner, who is part of the scrum team, who is knowledgable of scrum practices but is separate from the client/customer who understands the requirements more intimately and fully than the "internal" product owner.

I think the appropriate answer to your question is that it depends on the situation. For example, what is the product owner's level of knowledge of requirements & priorities, risks, etc., how experienced of a product owner are they? What is the nature of the new requirement? What is the nature of the relationship between the product owner and the client/end-user?

I hope the above clarifies some items for consideration when addressing this question.

--
Yazmine Darcy, MBA, PMP, PMI-ACP, CSM
Director of Operations, OSP International LLC
The Project Management PrepCast™ - www.project-management-prepcast.com
4 years 3 weeks ago #20234

Sadhana Shree

Sadhana Shree's Avatar

In sprint review if product owner identifies new requirement, does he need to put in product backlog for prioritization/validation by customer? (OR) PO can prioritize this in next sprint himself?