fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Free PMI Agile Certified Practitioner (PMI-ACP)® Exam Question of the Week

Free PMI Agile Certified Practitioner (PMI-ACP)® Exam Question of the Week 5 years 6 months ago #15183

  • Rachel Madrid
  • Rachel Madrid's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 56
  • Thank you received: 6
Here is our free PMI-ACP® Exam sample question of the week. This question is taken from The PM Exam Simulator at www.pm-exam-simulator.com/pmi-acp

After the end of the fourth sprint, the agile team members reported that they were unable to complete all user stories to be delivered in the sprint since the product owner pushed too many story points for the last sprint. As a result, the team had to work overtime and eventually got burned out. The product owner wants to hold the team accountable for the sprint failure. What is the best course of action for the team in this situation?

A. Accept responsibility for the failure but do not commit to a specific number of story points for the next sprint
B. Accept the responsibility for the failure and hold a retrospective to see how to improve the process for the next sprint
C. Apologize to the product owner and request doubling the team size to ensure the next sprint is completed properly
D. Not accept responsibility for the failure and hold the product owner accountable for pushing too many story points into the last sprint

HINT: Remember what reciprocal commitment is?
Last edit: by Rachel Madrid.

Free PMI-ACP® Exam Sample Question of the Week 5 years 6 months ago #15210

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
Accept the responsibility for the failure and hold a retrospective to see how to improve the process for the next sprint

Free PMI-ACP® Exam Sample Question of the Week 5 years 6 months ago #15237

  • Rachel Madrid
  • Rachel Madrid's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 56
  • Thank you received: 6
Correct Answer is B.

It is the responsibility of the team to meet commitments it makes. If the team does not meet the sprint goal, the team should accept responsibility for the failure and hold a retrospective to see how to improve the process for the next sprint so that a similar situation does not occur.


All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Want more PMI-ACP® exam sample questions? Simply sign up to our Free PMP Exam Simulator by visiting www.pm-exam-simulator.com/pmp-exam-simul...e-pmp-exam-simulator where we offer updated questions.

OSP International LLC has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI). As a PMI Registered Education Provider (R.E.P.), we have agreed to abide by PMI established quality assurance criteria.
The following user(s) said Thank You: Marco Rodrigues Grácio
Moderators: Yolanda MabutasJohn Paul BugarinSameer Menda

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login