Here is our free PMI-ACP® Exam sample question of the week. This question is taken from The PM Exam Simulator at
www.pm-exam-simulator.com/pmi-acp
An agile team has worked together on previous projects. In the team's last project, the greatest negative criticism was the inaccuracy of the estimates. When preparing estimates for a new project, what should an agile practitioner recommend that the team members do differently?
A. Deliberate extensively to completely eliminate uncertainty from the estimate
B. Fine tune approach but do not put too much effort to gain the maximum benefit from estimating
C. Lock down the budget, schedule, and scope to improve the accuracy
D. One team member should take primary responsibility for owning the estimate
Hint: Remember, in agile planning, progressive elaboration is used.
Answer will be posted by the end of the week!