fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Free PMI-ACP® Exam Sample Question of the Week

Free PMI-ACP® Exam Sample Question of the Week 5 years 7 months ago #14836

  • Rachel Madrid
  • Rachel Madrid's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 56
  • Thank you received: 6
Here is our free PMI-ACP® Exam sample question of the week. This question is taken from The PM Exam Simulator at www.pm-exam-simulator.com/pmi-acp

An agile team has worked together on previous projects. In the team's last project, the greatest negative criticism was the inaccuracy of the estimates. When preparing estimates for a new project, what should an agile practitioner recommend that the team members do differently?

A. Deliberate extensively to completely eliminate uncertainty from the estimate
B. Fine tune approach but do not put too much effort to gain the maximum benefit from estimating
C. Lock down the budget, schedule, and scope to improve the accuracy
D. One team member should take primary responsibility for owning the estimate

Hint: Remember, in agile planning, progressive elaboration is used.

Answer will be posted by the end of the week!
Last edit: by Rachel Madrid.

Free PMI-ACP® Exam Sample Question of the Week 5 years 7 months ago #14872

  • Abu Nasar
  • Abu Nasar's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 2
  • Thank you received: 0
B. Fine tune approach but do not put too much effort to gain the maximum benefit from estimating

The focus should be value delivery and not on estimation perfection.

Free PMI-ACP® Exam Sample Question of the Week 5 years 7 months ago #14873

  • Rachel Madrid
  • Rachel Madrid's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 56
  • Thank you received: 6
Congrats Ab Nasar! The correct answer is B.

With estimating, there is a point of diminishing returns, where additional effort put into estimation yields a minimal improvement in accuracy. Therefore, the team can fine-tune, but should not put in too much time or effort in estimating.

*****************************************************************************

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Want more PMI-ACP exam sample questions? Just go to free.pm-exam-simulator.com and try the PM Exam Simulator free for 7 days.

OSP International LLC has been reviewed and approved as a provider of project management training by the Project Management Institute (PMI). As a PMI Registered Education Provider (R.E.P.), we have agreed to abide by PMI established quality assurance criteria.
Last edit: by Rachel Madrid.
Moderators: Yolanda MabutasJohn Paul BugarinSameer Menda

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login