Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
A project started on April 1st, 2013 is expected to be completed by March 31st, 2014. During a project review on September 30th, 2013 it is determined that the total Actual Cost is $17.6 Million, the total Earned Value is $12.3 Million, and the total Planned Value is $12.8 Million. How much is the Schedule Variance?
A. $5.2 Million
B. $0.5 Million
C. -$0.5 Million
D. -$4.8 Million
HINT: SV = EV - PV
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 7 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.
Schedule Variance = Earned Value - Planned Value = $12.3 Million - $12.8 Million = -$0.5 Million.