fbpx

Reply: Free PMP® Exam Sample Question of the Week

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Free PMP® Exam Sample Question of the Week

Max. showing the last 6 posts - (Last post first)
6 years 2 months ago #12824

Mary Kathrine Padua

Mary Kathrine Padua's Avatar



Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

A project started on April 1st, 2013 is expected to be completed by March 31st, 2014. During a project review on September 30th, 2013 it is determined that the total Actual Cost is $17.6 Million, the total Earned Value is $12.3 Million, and the total Planned Value is $12.8 Million. How much is the Schedule Variance?

A. $5.2 Million
B. $0.5 Million
C. -$0.5 Million
D. -$4.8 Million

HINT: SV = EV - PV

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 7 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is C.

Schedule Variance = Earned Value - Planned Value = $12.3 Million - $12.8 Million = -$0.5 Million.

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login