Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
A project manager wants to ensure that all prospective sellers have a clear, common understanding of the technical requirements and contract requirements. Which of the following methods do you think is the most appropriate for the project manager?
A. Developing a qualified sellers list
B. Advertising
C. Holding a bidder conference
D. Independently estimating
HINT: These are meetings between the buyer and the prospective sellers.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.
Bidder conferences are meetings with prospective sellers prior to preparation of a bid. These meetings ensure a clear understanding of the procurement details.