Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
You are managing a bridge construction project. You have completed half of the project work. The total planned cost at this stage is $500. The actual physical work that has been completed at this stage is worth $400. You have already spent $1,000 on the project. What is the CPI?
A. 0.5
B. 4
C. 0.4
D. 1
HINT: CPI is the Cost Performance Index.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.
CPI = EV/AC EV = $400, AC = $1,000, PV = $500
Therefore CPI = 0.4