Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

You are managing a bridge construction project. You have completed half of the project work. The total planned cost at this stage is $500. The actual physical work that has been completed at this stage is worth $400. You have already spent $1,000 on the project. What is the CPI?

A. 0.5
B. 4
C. 0.4
D. 1

HINT: CPI is the Cost Performance Index.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a Project Management Institute (PMI)® Registered Education Provider.

Answer and Explanation:
The correct answer is C.

CPI = EV/AC EV = $400, AC = $1,000, PV = $500
Therefore CPI = 0.4
Last edit: by Mary Kathrine Padua.
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaTracy Shagnea, PMPJoe PangJohn Paul BugarinAmy MartinezLisa Sweeney PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on December 21/22 for just $179. Click to learn more... OR Click to watch a free session...