A project manager wants to use a technique for gathering information to anonymously identify risks and also to anonymously reach a consensus of experts. Which of the following would you suggest?
A. Root cause identification
B. Interviewing
C. Brainstorming
D. Delphi technique
HINT: The keyword here is "anonymously"!
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is D.
This technique is a way to reach a consensus of experts. Project risk experts participate in this technique anonymously.