Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

A project manager finds that a strike has been called on a particular date. There is a risk that the employees will not come to work on that day. The project manager decides not to take any action in spite of this because the likelihood of the strike is low. Which risk response strategy is the project manager following?

A. Accept
B. Avoid
C. Mitigate
D. Transfer

HINT: No risk management action is being planned here.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is A.

Because no risk management action is being planned here, this is an example of acceptance as a risk response strategy.