When should a project manager perform a risk review?
A. At the beginning of the project
B. Anytime an identified risk event is triggered
C. Throughout the project
D. When the project goes through a shift from concept to planning to implementation to close.
HINT: Risk can occur anytime in a project.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
, WWe are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.
Risk reviews are performed on a continuous basis throughout the project. This is because new risks usually evolve at every stage.