You are managing a bridge construction project. Half of the project work has been completed. The total planned cost at this stage was $2.5 million. The actual physical work that has been completed at this stage is worth $2.4 million. You have already spent $5.0 million on the project. What is the schedule variance?
A. $100,000
B. -$100,000
C. $2.6 million
D. $2.5 million
HINT: SV = EV - PV
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is B.
SV=EV-PV = $2.4 million - $2.5 million = -$100,000