fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question of the Week

Free PMP® Exam Sample Question of the Week 6 years 10 months ago #10844

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 352
  • Karma: 15
  • Thank you received: 122


Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

You are managing a bridge construction project. Half of the project work has been completed. The total planned cost at this stage was $2.5 million. The actual physical work that has been completed at this stage is worth $2.4 million. You have already spent $5.0 million on the project. What is the schedule variance?

A. $100,000
B. -$100,000
C. $2.6 million
D. $2.5 million

HINT: SV = EV - PV

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is B.

SV=EV-PV = $2.4 million - $2.5 million = -$100,000
Last edit: by Mary Kathrine Padua.

Free PMP® Exam Sample Question of the Week 6 years 10 months ago #10912

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
The selection B has typo, it is not -100,000 but as written -100,00 (missing a zero)
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login