Which document will you refer to if you are unable to understand a component of the WBS?
A. The Project Charter
B. The Scope Statement
C. WBS Dictionary
D. Statement of Work
HINT: This document provides details about the deliverables, activity, and scheduling information for each component.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.
You may refer to the WBS dictionary. This identifies all the components used in the WBS.