Which curve or line represents the cost baseline?
A. Slanted line
B. S-curve
C. Z curve
D. PQ curve
HINT: The cost is low at the beginning and end and high during the middle of the project.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is B.
An S-curve is typically used to represent a cost baseline. The cost is low at the beginning and end and high during the middle of the project.