Which curve or line represents the cost baseline?

A. Slanted line
B. S-curve
C. Z curve
D. PQ curve

HINT: The cost is low at the beginning and end and high during the middle of the project.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is B.

An S-curve is typically used to represent a cost baseline. The cost is low at the beginning and end and high during the middle of the project.