Which of the following may be considered as the outputs of the Perform Quality Assurance process?
A. Change requests, organizational process assets updates, project management plan updates
B. Requested changes, requested preventive actions, quality metrics
C. Quality management plan, quality metrics, quality baseline
D. Quality control measurements, recommended preventive actions
HINT: There are four outputs from the Perform Quality Assurance process.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a Project Management Institute (PMI)® Registered Education Provider.
Answer and Explanation:
The correct answer is A.
There are four outputs from the Perform Quality Assurance process which are: change requests, project management plan updates, project document updates, and organizational process assets updates.