Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
Which of the following processes is not part of project planning?
A. Acquire Project Team
B. Define Scope
C. Determine Budget
D. Develop Schedule
HINT: The project team is acquired during which stage of the project?
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is A.
Acquire Project Team is a process from the Executing process group. The rest of the choices are valid planning processes.