Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
Which of the following establishes quality metrics?
A. Quality planning
B. Quality baseline
C. Quality checklist
D. Quality assurance & quality control
HINT: Quality metrics are outputs of which process?
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP® Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a Project Management Institute (PMI)® Registered Education Provider.
Answer and Explanation:
The correct answer is A.
Quality metrics are outputs of the Plan Quality Management process, which is a planning component of the Project Quality Management Knowledge Area.