TOPIC: Free PMP® Exam Sample Question of the Week

Free PMP® Exam Sample Question of the Week 7 years 2 months ago #9374

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 349
  • Karma: 15
  • Thank you received: 122


Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

If SV = -800 and PV = 7000, how much is EV?

A. 6000
B. 8000
C. 6200
D. 9000

HINT: Use the Schedule Variance (SV) formula.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP® Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a Project Management Institute (PMI)® Registered Education Provider.

Answer and Explanation:
The correct answer is C.

SV = EV - PV, therefore EV = SV + PV = -800 + 7000 = 6200.
Last edit: by Mary Kathrine Padua. Reason: added (-) to SV= 800

Free PMP® Exam Sample Question of the Week 7 years 2 months ago #9431

  • CHANTAL TETU
  • CHANTAL TETU's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Karma: 1
  • Thank you received: 4
Not sure the answer is C. If the equation for SV is SV = EV - PV, then to find EV we must move PV on the other side which gives SV + PV = EV ... then the result would be 800 + 7000 = EV = 7800.... SV being positive and not negative in the question.

Free PMP® Exam Sample Question of the Week 7 years 2 months ago #9448

  • Ibrahim Elsharkawy
  • Ibrahim Elsharkawy's Avatar
  • Visitor
  • Visitor
from maths concepts EV= SV+PV

Free PMP® Exam Sample Question of the Week 7 years 2 months ago #9455

  • Don Sheahan
  • Don Sheahan's Avatar
  • Visitor
  • Visitor
The answer is definitely 7800

Free PMP® Exam Sample Question of the Week 7 years 2 months ago #9499

  • Yani Esbe
  • Yani Esbe's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 7
  • Thank you received: 2
Looks like typo for the question, should be -800 not 800
From math question will be : SV = EV - PV
Will become EV = -800 + 7000 = 6200

or as above comments (if not typo), EV = 7800
Last edit: by Yani Esbe.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login