Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
During which phase of the project would you suggest an integrated change control process?
A. Throughout the project
B. Initiation
C. Closure
D. Intermediate
HINT: The Perform Integrated Change Control process belongs to the Monitoring and Controlling process group.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is A.
This process is performed throughout the project, from initiation through closure.