Joe is currently performing a project post mortem. EVM shows SPI of 0.67 and CPI of 1. What does this mean to Joe ?
a. Joe's project was completed successfully. When the project ended, it was behind schedule and on budget.
b. Joe's project was completed unsuccessfully. When the project ended, it was behind schedule and on budget.
c. Joe's project was terminated before completion. When the project was terminated, it was on schedule and on budge.
d. Joe's project was terminated before completion.
This question is taken from the book -- 1000 PMP challenge questions by Mohit Arora. I am not able to understand how from the given information we could conclude that the project was terminated before completion. When is a project post mortem done, BEFORE the end of the project or AFTER the end of the project ? Thanks to help.