Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
Who determines which processes from the process group will be employed to achieve the desired objective?
A. The CEO
B. The most senior project team member
C. Project manager & the project team
D. A project initiator external to the project organization
HINT: Who is responsible for the effective management of the project?
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is C.
Project managers and their teams determine the project management approach and processes.