Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
Which of the following definitions of a project stakeholder do you think is most appropriate?
A. An entity that performs activities to accomplish objectives.
B. An entity whose interest may be affected as a result of the project execution.
C. One who is responsible for managing the project.
D. An enterprise whose employees are directly involved in doing the project work.
HINT: A stakeholder can be an individual, group or organization.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is B.
A stakeholder can be an individual, group or organization who may affect, or be affected by the outcome of the project.