TOPIC: Question Free PMP Exam Sample Question of the Week

Free PMP Exam Sample Question of the Week 1 year 2 weeks ago #8488

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 132
  • Karma: 5
  • Thank you received: 59


Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

Which of the following definitions of a project stakeholder do you think is most appropriate?

A. An entity that performs activities to accomplish objectives.
B. An entity whose interest may be affected as a result of the project execution.
C. One who is responsible for managing the project.
D. An enterprise whose employees are directly involved in doing the project work.

HINT: A stakeholder can be an individual, group or organization.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is B.

A stakeholder can be an individual, group or organization who may affect, or be affected by the outcome of the project.
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonMark Wuenscher, PMPTracy Shagnea, PMPJada Garrett

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Join the upcoming PMP Exam Coaching Class with Coach Dan Ryan. 6 Weeks of Live Coaching for just $59 ($79 after October 27). Learn More...