Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.
Maintaining a realistic project schedule is very important for the successful execution of a project. When you develop a schedule, which of the following items from the Project Scope Statement will impact the schedule?
A. Work Packages
B. Activity List
C. Assumptions and Constraints
D. Activity Attributes
HINT: Think about different parts of the Project Scope Statement.
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a PMI Registered Education Provider.
Answer and Explanation:
The correct answer is C.
Assumptions and constraints are very important items that impact the schedule. The Project Scope Statement contains this information.