Hello everyone! Here is this week's free PMP exam sample question from the PM Exam Simulator.

Maintaining a realistic project schedule is very important for the successful execution of a project. When you develop a schedule, which of the following items from the Project Scope Statement will impact the schedule?

A. Work Packages
B. Activity List
C. Assumptions and Constraints
D. Activity Attributes

HINT: Think about different parts of the Project Scope Statement.

All our questions are updated to the latest PMBOK® Guide standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a PMI Registered Education Provider.

Answer and Explanation:
The correct answer is C.

Assumptions and constraints are very important items that impact the schedule. The Project Scope Statement contains this information.
The following user(s) said Thank You: Carmen Pullian
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonMark Wuenscher, PMPTracy Shagnea, PMPJada Garrett

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

×
Join the upcoming PMP Exam Coaching Class with Coach Dan Ryan. 5 Weeks of Live Coaching for just $49. Learn More...